VUKOVAR-DALJ TRANSMISSION LINE PUT IN OPERATION VUKOVAR, July 29 (Hina) - A newly-constructed, 35-kV transmission line between Vukovar and Dalj was put in operation on Thursday. Present at today's opening ceremony were Vukovar-Srijem
County Prefect Rudolf Koenig and Osijek-Baranja Deputy Prefect Ivo Brzica and the head of the Croatian Power Supply (HEP) management, Damir Begovic. Begovic said with this latest investment the HEP has invested a total of six million German marks into the reconstruction of power generating facilities in the Croatian Danube River region. (hina) rml
VUKOVAR, July 29 (Hina) - A newly-constructed, 35-kV transmission
line between Vukovar and Dalj was put in operation on Thursday.
Present at today's opening ceremony were Vukovar-Srijem County
Prefect Rudolf Koenig and Osijek-Baranja Deputy Prefect Ivo Brzica
and the head of the Croatian Power Supply (HEP) management, Damir
Begovic.
Begovic said with this latest investment the HEP has invested a
total of six million German marks into the reconstruction of power
generating facilities in the Croatian Danube River region.
(hina) rml