ZUPANJA, Jan 17 (Hina) - The construction of access roads to a
second pontoon bridge over the Sava River near the eastern Croatian
town of Zupanja will be completed later on Wednesday, said a
spokesman for US troops with the NATO-led peace Implementation
Force (IFOR) in Zupanja, Captain Ed Richard.
The 300-metre bridge was set up at midday Wednesday and its
construction took 72 hours, Richard said, adding that the first
IFOR vehicles were expected to move across the bridge on Thursday
morning.
(hina) vm mm
172007 MET jan 96
Britanac, koji se borio u ukrajinskoj vojsci, osuđen u Rusiji na 19 godina
SAD planira otpustiti više od 80.000 zaposlenika Ministarstva za pitanja veterana
Trump zaprijetio Hamasu: Ako držite taoce, mrtvi ste
Najava događaja - fotografije - za četvrtak, 6. ožujka
Najava događaja - kultura - za četvrtak, 6. ožujka
Najava događaja - sport - za četvrtak, 6. ožujka
Najava - gospodarstvo - za četvrtak, 6. ožujka
Najava događaja - svijet - za četvrtak, 6. ožujka
Najava događaja - Hrvatska - za četvrtak, 6. ožujka
Trener Lyona zbog napada na suca suspendiran do 30. studenog