DRNIS, April 30 (Hina) - A 10 KW power transmission line from Zitnic - Sedmaric was put to use for the first time in the village of Sedmaric near Drnis Wednesday.
DRNIS, April 30 (Hina) - A 10 KW power transmission line from Zitnic
- Sedmaric was put to use for the first time in the village of
Sedmaric near Drnis Wednesday. #L#
The construction of the 4000 metres long power transmission line
was done by the Croatian Power Supply company, while the project was
financed by the U.S. Agency for International Development. The
project is valued at 2.8 million kuna.
The U.S. has so far assisted the Drnis area on the basis of a
Memorandum of Understanding signed by the Town of Drnis and the
USAID enabling reconstruction of the water supply, the
introduction of gas pipelines in some areas, etc.
(Hina) sp it sb