ZUPANJA, Nov 23 (Hina) - All major works on the reconstruction and +building of a bridge across the Sava River between Zupanja, +Croatia, and Orasje, northern Bosnia-Herzegovina (BH), have been +completed, Djordje Momcilovic,
supervisor of the works, said on +Monday.+ A technical check-up will be carried out on December 8 and 9, while +an inspection certificate will be issued shortly afterwards, in +keeping with deadlines.+ The newly built section runs 304m, while the bridge's entire length +is 774m.+ The chief contractor was "Djuro Djakovic Montaza", a Croatian +company from Slavonski Brod, assisted by other companies from +Croatia and BH.+ The principal investors in the US$ 6.5 million-worth +reconstruction works were Croatian Roads and BH's Transport +Projects Implementation Directorate.+ Works on a border crossing on the Croatian side are being completed +simultaneously with the completion
ZUPANJA, Nov 23 (Hina) - All major works on the reconstruction and
building of a bridge across the Sava River between Zupanja,
Croatia, and Orasje, northern Bosnia-Herzegovina (BH), have been
completed, Djordje Momcilovic, supervisor of the works, said on
Monday.
A technical check-up will be carried out on December 8 and 9, while
an inspection certificate will be issued shortly afterwards, in
keeping with deadlines.
The newly built section runs 304m, while the bridge's entire length
is 774m.
The chief contractor was "Djuro Djakovic Montaza", a Croatian
company from Slavonski Brod, assisted by other companies from
Croatia and BH.
The principal investors in the US$ 6.5 million-worth
reconstruction works were Croatian Roads and BH's Transport
Projects Implementation Directorate.
Works on a border crossing on the Croatian side are being completed
simultaneously with the completion of works on the bridge.
(hina) ha