ZAGREB/MOSCOW, Sept 24 (Hina) - Government and transport company representatives of participants in the Druzba Adria project in Moscow on Tuesday harmonised the final text of an agreement on cooperation in the integration of the
Druzba and Adria oil pipelines into the European pipeline grid, Croatia's JANAF pipeline said.
ZAGREB/MOSCOW, Sept 24 (Hina) - Government and transport company
representatives of participants in the Druzba Adria project in
Moscow on Tuesday harmonised the final text of an agreement on
cooperation in the integration of the Druzba and Adria oil
pipelines into the European pipeline grid, Croatia's JANAF
pipeline said. #L#
It has been agreed the agreement will be signed in Croatia by year's
end.
It is estimated the transport of Russian oil via the Ukraine,
Belarus, Slovakia, and Hungary to the Croatian terminal in Omisalj
will start as early as late 2003.
The Russian side should guarantee the transport of five-, ten-, and
15-million-ton shipments, while JANAF would finance the
reconstruction of sections of the Sisak-Omisalj pipeline with
US$20 million.
(hina) ha sb