Of a total of 165 segments of the bridge span, 134, with the total length of 1,850 metres, have been installed, leaving 31, with the total length of 550 metres to be installed.
The 2.4 kilometre bridge is expected to be opened by the end of July or in early August, three years after Chinese construction workers started work in the Bay of Mali Ston.
The Pelješac Bridge, worth €550 million, of which 357 million is provided by the EU, is being built by the China Road and Bridge Corporation.