FILTER
Prikaži samo sadržaje koji zadovoljavaju:
objavljeni u periodu:
na jeziku:
hrvatski engleski
sadrže pojam:

Construction work begins on Baranja gas supply network

Autor: ;vmic;
BELI MANASTIR, Sept 5 (Hina) - Parliament Speaker Vladimir Seks on Tuesday formally opened construction work on a KN62 million (EUR8.4 million) gas supply network in the eastern region of Baranja.
BELI MANASTIR, Sept 5 (Hina) - Parliament Speaker Vladimir Seks on Tuesday formally opened construction work on a KN62 million (EUR8.4 million) gas supply network in the eastern region of Baranja.

The estimated length of gas pipelines for the regional capital Beli Manastir and seven municipalities is 460 kilometres. The project is expected to be completed in five years.

The construction of the first section of the pipeline for Beli Manastir and its suburb of Secerana started today. The section is 74.5 kilometres long and its construction costs KN8.5 million (EUR1.15 million).

(Hina) vm

An unhandled error has occurred. Reload 🗙