Zagreb, August 16, 2021 – Institut IGH, d.d. and BINA - ISTRA d.d. signed a contract today with a total value of HRK 3,903,382.50 (VAT not included in the price). The subject of the contract is design work of project documentation and implementation of administrative procedures for Sub-phase 2B2-3 supplement to the complete profile of the Istrian Y highway - A9 - new structures viaduct Limska Draga and bridge Mirna to supplement the complete profile of sections where these facilities are located, ie Kanfanar-Medaki and Nova Vas - Visnjan.
Institut IGH, d.d. as a designer, will complete all projects within 300 calendar days from the date of issuing the order for the start of design, while the deadline for obtaining all building permits is 65 calendar days or a total of 365 calendar days.
INSTITUT IGH, JSC
Source of information:
INSTITUT IGH, d.d.
10000 Zagreb, Janka Rakuše 1
Tel: +385 01 6125-789
Fax: +385 01 6125 415
e-mail: IR@igh.hr