ZAGREB, Jan 28 (Hina) - Drilling works on the right tube of the Bristovac tunnel on the Sveti Rok-Maslenica section of the Zagreb-Split highway were completed on Tuesday, the Croatian Highways company reported.
ZAGREB, Jan 28 (Hina) - Drilling works on the right tube of the
Bristovac tunnel on the Sveti Rok-Maslenica section of the Zagreb-
Split highway were completed on Tuesday, the Croatian Highways
company reported. #L#
Bristovac is a two-tube tunnel. The right tube is 629 metres long,
while the left one is 672 metres long. The tunnel is being built by
Viadukt from Zagreb and the total value of the contract is some
9,120,000 euros not including VAT.
The deadline for the construction of the tunnel is June 30 this
year.
(hina) rml sb